By Erica Kearns
After an explosive demolition last week, crews continue to clean up the remains of the Hartland Bridge. Expecting to have all of the debris from the old structure completely removed in less than two weeks, crews are working seven days a week to meet their deadline. Nearly half of the steel structure has already been removed from the Elk.